WORKING FOR YOU
Downtown Traffic Impacts
42nd Ward Street Closures and Construction Notices
WORKING FOR YOU
42nd Ward Street Closures and Construction Notices
Utility Work
Temporary Bus Stop Elimination
Until March 2024, the westbound bus stop at Grand and St. Clair will be temporarily removed.
State & Lake Utility Relocations
Utility companies began relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations. At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed. Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM on weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work during overnight hours.
Bridges, Tunnels, & Viaducts
Grand Avenue Bridge Project
The Grand Avenue Bridge project will be completed at the beginning of 2023. That said, work on Saturday, December 17 and Sunday, December 18 will begin at 7am.
Randolph Street Viaduct:
CDOT restarted viaduct repairs on Randolph, between Columbus and Field. Work hours are Monday-Friday, from 8am-8pm. Throughout the project, at least one lane of eastbound traffic will be open. Westbound lanes will not be disrupted. The project is expedited to be completed mid-November (weather dependent).
Dearborn Street Bridge:
CDOT has scheduled emergency work on the Dearborn Bridge to begin June 13 (weather dependent). They will be conducting the following work:
The project is expected to be completed in December 2022 (weather dependent). The bridge will be reduced to one lane of traffic/sidewalk at a time. Bike traffic will be detoured to Clark Street via the north side of Upper Wacker Drive.
Chase Tower Clark Street Tunnel:
In mid-July, Berglund Construction began repairs on the Chase Tower Clark Street tunnel at 23 S. Clark Street. The project scope consists of repairing Chase’s below-grade tunnel structures that cross below Clark Street at 23 S. Clark St, and will require excavation of Clark Street in that area to access the tunnel structures to perform repairs. There will be one lane of southbound traffic open at all times. Berglund will have flaggers and barricades in-place throughout the project. The project will last 26 months. Berglund would like to begin mid-June. Work hours will be Monday-Friday, from 8am-5pm.
Developments
151 N Michigan:
Power Construction has begun demolition of Millennium Park Plaza located at 151 N Michigan Avenue. During the demolition, the following will be closed:
Pedestrians will be directed to use projected walkways that are placed in the curb lanes on Randolph and Michigan. Demolition is expected to be completed in early February.
354 North Union:
The Onni Group is constructing a 33-story residential building with 373 units. Work hours will be 8am-8pm, daily. Parking will be prohibited on North Union, from West Kinzie to the cul-de-sac west thereof throughout the project. All construction equipment and vehicles will be staged on the Onni Group’s property. This project will take approximately two years to complete.
751 N. Hudson and 451 W Chicago:
LG Construction continues work on 751 N. Hudson Avenue and 451 W. Chicago Avenue, which are adjacent parcels. Work hours will be 8am-5pm, Monday-Friday. Throughout the project, the following will be closed:
There will be a protected pedestrian walkway in the curb lane on the south side of Chicago Avenue, from Hudson Avenue to Sedgwick Street. This project is expected to take 18 months to complete (weather dependent).
311 W Huron:
In June, ARCO Murray began construction of a new building at 311 W. Huron Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours). Throughout the project, the following City right-of-way will be occupied:
The project is expected to be completed in September 2023 (weather dependent). Peoples Gas Main Installation Project: Bellevue, from Lake Shore Drive to Rush. Sidewalk restoration on both sides of Bellevue, from Lake Shore Drive to Rush will begin the week of October 17.
Cassidy Tire:
Construction of the 33-story mixed-use building is underway. Throughout construction, McHugh Constriction will occupy the curb lane on the west side of Canal along 344/350 N. Canal Street’s property line. The construction company has leased the area north of the building from the railroad to use as a staging area. Additionally, they will use the parking lot south of the building as a staging area too. All work is expected to take 24 months to complete (weather dependent).
150 E Ontario:
W.E. O’Neil began construction of a 23-story building at 150 East Ontario Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours). Some weekend work will occur. Throughout the project, the following will be closed:
Pedestrians will be directed to the sidewalk on the south side of the street at Ontario/Michigan and Ontario/St. Clair. The entire project is expected to take 23 months to complete.
535 N. St. Clair Street:
Demolition of 535 N St. Clair is completed. LendLease has mobilized for construction and they have began pouring caissons. Throughout the project, there will be a protected pedestrian canopy on the north side of Grand, from St. Clair to a point 100′ east thereof. The entire project is expected to be completed at the beginning of 2024.
214 West Erie Street Renovations:
On Monday, December 13, Crane Construction began renovations of 214 West Erie Street. During construction, the following will be closed:
This project is expected to be completed summer of 2023 (weather dependent).