WORKING FOR YOU
Downtown Traffic Impacts
42nd Ward Street Closures and Construction Notices
WORKING FOR YOU
42nd Ward Street Closures and Construction Notices
Street Sweeping
During street sweeping season (April 1 to mid-November) the Chicago Department of Streets and Sanitation uses mechanical street sweepers to remove debris and litter from streets, weather permitting. Throughout the season, DSS deploys mechanical street sweepers at regularly scheduled times to clear debris from Chicago streets. Starting this week, dozens of street sweepers have begun clearing the debris and leaves that have accumulated during winter months on both residential and arterial streets.
On weekdays, from 9am to 2pm, this Sweeper Tracker map will show real-time locations of city street sweepers. For more information, please review the 42nd Ward Map and street sweeping schedule. Residents can also call 311 to find the dates and locations of street sweeping in their area.
Please check for the bright orange signs announcing temporary parking restrictions. These signs are posted two days prior to scheduled street sweeping events. Some streets also have permanently posted signs that specify a once-per-week period when parking is prohibited for street sweeping.
Utility Work
PGL River North Project:
Peoples Gas plans to begin a gas main project in River North. PGL will be working at the following locations:
The project is expected to begin at the end of July. It will be completed at the end of 2023.
Temporary Bus Stop Elimination:
Until March 2024, the westbound bus stop at Grand and St. Clair will be temporarily removed.
Peoples Gas Project: Clark and Adams:
PGL began work on Clark (Monroe to Jackson) and Adams (LaSalle to Clark) earlier this month. There will be temporary lane closures on Clark and Adams during permit hours but traffic will be maintained at all times. Work days/hours are Monday-Saturday, from 8am-5pm. This project is expected to be completed in October 2023.
State & Lake Utility Relocations:
Utility companies began relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations. At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed. Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM on weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work during overnight hours.
Utility openings on North Water Street: Related Midwest Test Holes
Related Midwest will be digging test holes at the following locations/dates/times:
Traffic flow will be maintained throughout the project.
Tower Cranes & Helicopter Lifts
Crane Lift: 153 W Ohio
Stevenson Crane was hired to lift cell equipment onto the roof of 153 W Ohio Street. The lift will occur on Saturday, July 29 (Back-up day July 30), from 8am to 4pm. During the lift, the following will be closed:
The curb lane on the northside of Ohio will be posted NPTZ and used for eastbound traffic.
Bridges, Tunnels, & Viaducts
Grand Avenue Bridge Project:
The Chicago Department of Transportation is replacing the black rubber mats on the sidewalks on both sides of the Grand Avenue Bridge. Repairs are expected to be completed by mid-August.
Kennedy Expressway Bridge Rehabilitation
The Illinois Department of Transportation (IDOT) began rehabilitation of the Kennedy Expressway (Interstate 90/94), from the Edens Expressway (Interstate 94) junction to West Ohio Street
The project consists of rehabilitating 36 bridge structures and the Reversible Lane Access Control (REVLAC) system, replacing overhead sign-structures, installing new signage and modernized LED lights, pavement patching and structural painting. Additionally, Hubbard’s Cave, from Grand Avenue to Wayman Street, will be painted and new LED lighting installed. This project will take place over three consecutive construction seasons and consist of three stages. The following will occur during stage one:
Stage I – Inbound Kennedy
To help minimize the impact to traffic the reversible express lanes will remain open in the inbound direction, while two mainline inbound lanes will be closed at a time. Motorists should expect lane shifts and overnight lane closures and various ramp closures. Later this summer, painting and installation of new LED lighting will begin on inbound Hubbard’s Cave, between Ohio and Lake streets. Construction is anticipated to be completed later this fall, with all lanes and ramps reopening and the express lanes resuming normal operations. Please click here to learn more about the Kennedy Expressway Bridge Rehabilitation, and stay tuned to Reilly Reports for future updates.
Maggie Daley Summer Camp Drop-off:
Due to the Randolph Street viaduct project, CDOT placed a temporary pick-up/drop-off area on the south side of Randolph, between Field and Harbor for Summer Camp at Maggie Daley Park. During the 30 minute drop-off and pick-up periods, CDOT will have barricades and traffic control in-place to help direct traffic. One lane of traffic in each direction will be maintained at all times on Randolph, from Field to Harbor. This traffic configuration will be in-place until August 4, 2023.
Dearborn Street Bridge:
Due to equipment and material procurement problems, the Dearborn Street Bridge project will be completed in September 2023 (weather dependent). One lane of traffic will remain open at all times.
Randolph Street Viaduct Repair:
CDOT will be performing repairs at Randolph Street Viaduct (East bound lanes only) between Columbus Dr. and Field Blvd.
Chase Tower Clark Street Tunnel Project:
In mid-July, Berglund Construction began repairs on the Chase Tower Clark Street tunnel at 23 S. Clark Street. The project scope consists of repairing Chase’s below-grade tunnel structures that cross below Clark Street at 23 S. Clark St, and will require excavation of Clark Street in that area to access the tunnel structures to perform repairs. There will be one lane of southbound traffic open at all times. Berglund will have flaggers and barricades in-place throughout the project. The project will last 26 months. Berglund would like to begin mid-June. Work hours will be Monday-Friday, from 8am-5pm.
Developments
354 North Union Construction
The Onni Group is constructing a 33-story residential building with 373 units. Work hours will be 8am-8pm, daily. Parking will be prohibited on North Union, from West Kinzie to the cul-de-sac west thereof throughout the project. All construction equipment and vehicles will be staged on the Onni Group’s property. This project will take approximately two years to complete.
431 N Dearborn Façade Project
Crane construction began a façade project at 431 N Dearborn this week. Throughout the project, the sidewalks adjacent to the building on Dearborn and Hubbard will be closed. Pedestrians are directed to walk in a projected pedestrian walkways in the curb lanes. The project is expected to be completed in October 2023 (weather dependent).
Demolition of 1043 N Rush Street will begin on Monday, March 6. Work hours will be Monday-Friday, from 8am to 5pm. Throughout the the demolition process, the sidewalk in front of 1043 N Rush Street will be closed to pedestrian traffic. Pedestrians will be redirected at Bellevue/Rush and Cedar/Rush. The demolition process is expected to last three weeks. After demolition is complete, the construction of a new two-story building will begin.
225 W Randolph Renovation:
The Onni Group began renovating 225 W Randolph. Throughout the project, there will be pedestrian canopies at the following locations:
This project is expected to be completed July 2024.
151 N Michigan:
Power Construction has begun demolition of Millennium Park Plaza located at 151 N Michigan Avenue. During the demolition, the following will be closed:
Pedestrians will be directed to use projected walkways that are placed in the curb lanes on Randolph and Michigan. Demolition is expected to be completed in early February.
751 N. Hudson and 451 W Chicago:
LG Construction continues work on 751 N. Hudson Avenue and 451 W. Chicago Avenue, which are adjacent parcels. Work hours will be 8am-5pm, Monday-Friday. Throughout the project, the following will be closed:
There will be a protected pedestrian walkway in the curb lane on the south side of Chicago Avenue, from Hudson Avenue to Sedgwick Street. This project is expected to take 18 months to complete (weather dependent).
311 W Huron:
In June, ARCO Murray began construction of a new building at 311 W. Huron Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours). Throughout the project, the following City right-of-way will be occupied:
The project is expected to be completed in September 2023 (weather dependent). Peoples Gas Main Installation Project: Bellevue, from Lake Shore Drive to Rush. Sidewalk restoration on both sides of Bellevue, from Lake Shore Drive to Rush will begin the week of October 17.
Cassidy Tire:
Construction of the 33-story mixed-use building is underway. Throughout construction, McHugh Constriction will occupy the curb lane on the west side of Canal along 344/350 N. Canal Street’s property line. The construction company has leased the area north of the building from the railroad to use as a staging area. Additionally, they will use the parking lot south of the building as a staging area too. All work is expected to take 24 months to complete (weather dependent).
150 E Ontario:
W.E. O’Neil began construction of a 23-story building at 150 East Ontario Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours). Some weekend work will occur. Throughout the project, the following will be closed:
Pedestrians will be directed to the sidewalk on the south side of the street at Ontario/Michigan and Ontario/St. Clair. The entire project is expected to take 23 months to complete.
535 N. St. Clair Street:
Demolition of 535 N St. Clair is completed. LendLease has mobilized for construction and they have began pouring caissons. Throughout the project, there will be a protected pedestrian canopy on the north side of Grand, from St. Clair to a point 100′ east thereof. The entire project is expected to be completed at the beginning of 2024.
15 E Oak Street: Facade Project:
Early this week, a facade project began at 15 E Oak Street. Throughout the project, the sidewalk on the south side of Oak, from State to Rush will be closed. A protected pedestrian walkway will be in-place in the curb lane. The project is expected to be completed October 2023.
120 E Oak Street Facade Project
Summit Design + Build will begin a facade project at 120 E Oak Street on Tuesday, May 30. Works hours will be Monday thru Saturday, from 8am-5pm. Throughout the project, the sidewalk adjacent to the building will be closed. It will be covered by construction fencing. Pedestrians will be pushed to a protected pedestrian path in the curb lane. Deliveries will occur between before 9am and debris will be removed between 8am-9am. There will be a gate at the east end of the fencing for deliveries and debris removal. The project will be completed in early November.
Murphy Auditorium Renovation
Driehaus Museum purchased the Murphy Auditorium at 50 E Erie and plans to begin renovations in June. Work hours are Monday-Friday, from 8-4pm. They plan to complete the following interior alterations:
Throughout the project, the following will be in-place:
They will need to use a small crane periodically throughout the project to lift materials onto the roof that can’t fit through the doorway. Driehaus will notify us in advance of installation of a small crane.
214 West Erie Street Renovations
On Monday, December 13, Crane Construction began renovations of 214 West Erie Street. During construction, the following will be closed:
This project is expected to be completed in early 2023 (weather dependent).